Nigeria’s electricity supply from the national grid plunged by 81.5 per cent to 675 megawatts (MW) at 1pm on Monday, down from 3,647MW at noon, following a reduction in the number of power plants supplying the grid from 21 to 12.
The sharp decline prompted electricity distribution companies, including Abuja Electricity Distribution Company (AEDC) and Ikeja Electric, to notify customers of supply disruptions linked to challenges on the national grid.
Data from the Nigerian Independent System Operator showed that 21 power plants were supplying electricity to the grid at noon, generating a combined 3,647MW.
However, by 1pm, only 12 plants remained online, while total generation dropped by 2,972MW to 675MW within an hour.
Among the power plants reported to have gone offline were Azura, Egbin, Jebba and Kainji hydroelectric power plants.
The decline came after relatively strong supply levels earlier in the day, with grid generation reaching 4,331MW at 1am and 4,458MW at 6am. Supply subsequently dropped to 3,647MW by noon before plunging to 675MW at 1pm.
Electricity supply later recovered to 2,150MW by 5pm, representing an increase of 1,475MW from the 1pm figure. However, generation remained significantly below the morning peak.
In a public notice issued on Monday, AEDC informed customers that electricity supply from the Transmission Company of Nigeria (TCN) had been disrupted due to a challenge affecting the national grid.
The company said TCN’s technical team was working to restore grid stability, adding that electricity supply was gradually being restored to its feeders.
“We assure you that efforts are ongoing to restore full supply across our franchise area as soon as the situation permits,” AEDC stated, apologising to customers for the inconvenience caused by the disruption.
Similarly, Ikeja Electric attributed the reduction in electricity supply across its network to a shortfall in the volume of power allocated to it from the national grid.
The distribution company said it was engaging relevant stakeholders to improve the available supply.
It also assured customers that it would continue to distribute the electricity received from the grid as efficiently and equitably as possible.